ADB attaches strings to continued funding for BRT Red Line project
KARACHI: The never-ending construction of the Bus Rapid Transit (BRT) Red Line, which has become a nightmare for citizens and a source of embarrassment for the government, now appears to have started to annoy the project financier Asian Development Bank (ADB) as it has made the latest extension of the delayed scheme’s loan conditional on achieving key milestones by April 2027, it has emerged. Official sources told Dawn that things have moved faster this time, with TransKarachi, the project’s implementing agency, having achieved most of the milestones. It is hoped that the remaining targets will be met within the stipulated time frame. “At the last meeting with the ADB, its officials conveyed that work on the project is not progressing at a satisfactory pace,” a government official told Dawn on the condition of anonymity. “So, the ADB agreed to extend the loan facility but also set a condition that we must achieve certain milestones within 10 months. The deadline expires in April 2027.” The official, however, expressed confidence that all required milestones would be met on time to fulfil the ADB’s conditions and secure further funding without any hurdles. Irked by slow progress, Asian Development Bank sets April 2027 deadline for project implementation agency to achieve ‘certain milestones’, say officials He then referred to the designated “milestones”, including completing all processes and putting everything in place for a fresh contract for the 12.8-kilometre stretch from Numaish to Mosamiyat, known as Lot 2. The government had cancelled the contract in April “due to delays in the project’s execution by the contractor”. “That process has been completed and work is in progress. The structural works under the project in this phase include elevated U-turns, flyovers, underpasses and BRT lanes,” the official added. The tenders for the remaining milestones had also been floated, he said, adding that “things are in process” and were expected to take final shape in the coming weeks. One of them, he said, included procurement for the construction of the underground bus staging facility at Numaish. “The Karachi Goan Association Ground near Numaish is the designated site for an underground BRT bus staging facility under the Karachi BRT Red Line Project. Here, a staging facility of around 100 BRT buses would be constructed underground,” he added. He referred to another component of the project, which is relocation of Pakistan Airports Authority airside perimeter fence and allied works of the Jinnah International Airport and marked as “milestone” and must be achieved by April 2027. “The process of this portion is already underway and we hope that it would be finished much before the stipulated timeline,” added the official. Launched in March 2022, the BRT Red Line has faced repeated setbacks, driving its cost up to $725 million amid rising construction costs and the depreciation of the Pakistani rupee. Meanwhile, the prolonged construction has turned the project into a nightmare for hundreds of thousands of commuters travelling along the route, as well as residents living in the surrounding areas. The project has drawn considerable criticism, prompting the city mayor and government spokesperson, Barrister Murtaza Wahab, to publicly acknowledge in December 2024 that the prolonged construction of the BRT Red Line had become a “source of embarrassment” for the PPP government. With the project facing intermittent hiccups, questions remain about whether the deadline can be met, which, according to TransKarachi, has now been set for June 2028. “For Lot-2, an 18-month deadline has been set for completion of the particular stretch,” said the official. “For Lot-1, December 2026 has been set as the deadline for completion of its main corridor while the stretch to Malir Halt is expected to be completed by April 2027. The Bagh-i-Karachi [formerly known as Aladin Park] section is scheduled for completion by July 2027.” Published in Dawn, November 17, 2026
- Siyasi17 Kas 05:05
ADB attaches strings to continued funding for Karachi BRT Red Line project
KARACHI: The never-ending construction of the Bus Rapid Transit (BRT) Red Line, which has become a nightmare for citizens and a source of embarrassment for the government, now appears to have started to annoy the project financier Asian Development Bank (ADB) as it has made the latest extension of the delayed scheme’s loan conditional on achieving key milestones by April 2027, it has emerged. Official sources told Dawn that things have moved faster this time, with TransKarachi, the project’s implementing agency, having achieved most of the milestones. It is hoped that the remaining targets will be met within the stipulated time frame. “At the last meeting with the ADB, its officials conveyed that work on the project is not progressing at a satisfactory pace,” a government official told Dawn on the condition of anonymity. “So, the ADB agreed to extend the loan facility but also set a condition that we must achieve certain milestones within 10 months. The deadline expires in April 2027.” The official, however, expressed confidence that all required milestones would be met on time to fulfil the ADB’s conditions and secure further funding without any hurdles. Irked by slow progress, Asian Development Bank sets April 2027 deadline for project implementation agency to achieve ‘certain milestones’, say officials He then referred to the designated “milestones”, including completing all processes and putting everything in place for a fresh contract for the 12.8-kilometre stretch from Numaish to Mosamiyat, known as Lot 2. The government had cancelled the contract in April “due to delays in the project’s execution by the contractor”. “That process has been completed and work is in progress. The structural works under the project in this phase include elevated U-turns, flyovers, underpasses and BRT lanes,” the official added. The tenders for the remaining milestones had also been floated, he said, adding that “things are in process” and were expected to take final shape in the coming weeks. One of them, he said, included procurement for the construction of the underground bus staging facility at Numaish. “The Karachi Goan Association Ground near Numaish is the designated site for an underground BRT bus staging facility under the Karachi BRT Red Line Project. Here, a staging facility of around 100 BRT buses would be constructed underground,” he added. He referred to another component of the project, which is relocation of Pakistan Airports Authority airside perimeter fence and allied works of the Jinnah International Airport and marked as “milestone” and must be achieved by April 2027. “The process of this portion is already underway and we hope that it would be finished much before the stipulated timeline,” added the official. Launched in March 2022, the BRT Red Line has faced repeated setbacks, driving its cost up to $725 million amid rising construction costs and the depreciation of the Pakistani rupee. Meanwhile, the prolonged construction has turned the project into a nightmare for hundreds of thousands of commuters travelling along the route, as well as residents living in the surrounding areas. The project has drawn considerable criticism, prompting the city mayor and government spokesperson, Barrister Murtaza Wahab, to publicly acknowledge in December 2024 that the prolonged construction of the BRT Red Line had become a “source of embarrassment” for the PPP government. With the project facing intermittent hiccups, questions remain about whether the deadline can be met, which, according to TransKarachi, has now been set for June 2028. “For Lot-2, an 18-month deadline has been set for completion of the particular stretch,” said the official. “For Lot-1, December 2026 has been set as the deadline for completion of its main corridor while the stretch to Malir Halt is expected to be completed by April 2027. The Bagh-i-Karachi [formerly known as Aladin Park] section is scheduled for completion by July 2027.” Published in Dawn, November 17, 2026
Okumaya devam et
ilgili gelişmeler- Aynı ülke gündemicanlı
10 cops martyred, 18 terrorists killed as police party comes under attack in KP's Kohat
Pakistan5 olay3 sa önce - Aynı ülke gündemicanlı
Counterfeit medicines, vaccines in rural areas alarm lawmakers
Pakistan1 olay6 sa önce - Aynı ülke gündemicanlı
Entry of tourists to Saiful Muluk Lake banned amid snowfall
Pakistan1 olay6 sa önce - Aynı ülke gündemicanlı
Five-year-old girl dies of rabies in Karachi, taking Sindh’s toll to 44
Pakistan1 olay6 sa önce - Aynı ülke gündemicanlı
796 Afghans arrested in first week of November
Pakistan1 olay6 sa önce - Aynı ülke gündemicanlı
Italy-Pakistan Cooperation: Summit in Islamabad to Strengthen Ties
Pakistan1 olay17 sa önce